NEWS FLASH

Ljubljana Airport has accomplished the most important development part of its foremost apron renovation undertaking. The works, which started in March, concerned the alternative of roughly 37.000 sq. metres of worn pavement, together with 16.000 sq. metres of recent concrete plane parking stands and 21.000 sq. metres of recent asphalt pavement. In consequence, all plane stands adjoining to the terminal have returned to service, enhancing operational flexibility and plane dealing with through the peak summer time season.
Building is now persevering with on the northwestern part of the primary apron and stays on schedule for completion in October 2026. As soon as completed, the upgraded apron will accommodate 22 Code C plane stands, 4 Code D stands and two Code E stands, strengthening Ljubljana Airport’s capability for future development.